Under Construction - Urbana, Brooklyn Park, MN

There are three (3) separate components to this development:

  • 94th Ave. N Street & Utility Expansion - Installation of approximately 1,100 LF of new road construction. Work to include sidewalks and bituminous trail. Utility work to include water main, sanitary and storm sewer extensions.

Currently the balance of perimeter strip footings were poured and wall panels are being set; we will be pouring them in the following weeks. Utilities have had a good start, sanitary sewer and water main are in the road. We've started the cut for the deep sanitary sewer line at the SE corner along 93rd ave.

  • Urbana Place Senior Living - New construction of 100 unit assisted living facility on a partial slab on grade foundation with 24,000 SF of underground parking. Finished area is 123,241 SF wood framed four story.

We are excited to announce the ground breaking for Urbana Place Senior Living will take place September 27th, 2018.

Construction update for Urbana Place; prep and install of thin brick and stone on west side, south of canopy. Finish carpenters are working on base on 4th floor in the corridor, trim in common area around windows and 1st floor they’re unboxing cabinets. The siders are installing Nichiha, fascia and trim boards on the west side of the building. Flooring subcontractor is grouting common area rooms on 1st floor and installing vinyl in units on 1st, elevator lobby on 2nd and carpeting units on 2nd and 3rd while the ceiling crew works on padding out 3rd and 2nd floor ceilings. Plumbers are setting fixtures on 2nd and HVAC crew is working on furnace rooms on 2nd and 1st and installing fresh air louver in garage.

  • Urbana Court Apartments - 314,782 SF three story wood framed 207-unit apartment over a 77,864 SF underground parking structure.