Despite the extreme cold and snow we have experienced so far this winter, the steel erection crew has made good progress on the building. The roof system will be completed this week and if the weather holds, we should have the structure enclosed within the next couple weeks. Once this happens, we will fire up the temp heat so we can proceed with the underground, slab and office framing.
The anticipated completion is projected to be in late March.